Source : IDRW
News By : : Flight International
Two of the Indian Aeronautical Development Agency’s Tejas Mk 1 light combat aircraft will be ready for induction by March 2012.So far, 1,659 flight tests of the Tejas have been conducted, said defence minister AK Antony. The Indian Air Force has ordered forty Mk 1s, 20 with “initial operating clearance standard” and 20 with “final operation clearance standard”, he added.
Antony’s comments were in response to a query from a member of parliament about the status of the indigenous fighter programme. The Tejas Mk 1, which is produced by Hindustan Aeronautics (HAL), received initial operational clearance on 11 January.
He also discussed the costs of the programme. In 2001, this was estimated at Indian rupees (Rs) 33 billion ($740 million), but cost overruns added an additional Rs24.8 billion to this.